Golden 24 hours principle ----all the responses should be done within 24 hours!Step.1 Order Step.2 DFMEA Step.3 Tooling BOM Form Step.4 Tooling 2D DrawingStep.5 Cutting Tooling Notice Step.6 Weekly Report Step.7 Tooling 3D drawing Step.8 Dimension Report of T1 sampleStep.9 Packing Information Step.10 CDStep.11 3000 cycles testing for toolin...
timeTue, 02 Jan 2018 13:18:53 GMT
Step.1 Order1. Confirm Order2. Issuer PI3. Provide Engineers with part drawings and special requirements
timeTue, 02 Jan 2018 13:21:32 GMT
Step.2 DFMEADFMEA(Design Failure Mode & Effect Analysis ) should be prepared before the 2D tooling design ,which should include P/L, Gate location, Ejector pins and the basic structure of tooling as well as the comments for any parts design defects. This is a good way to save much time and cost for tooling design and fabrication.
timeTue, 02 Jan 2018 13:22:29 GMT
DFMEA REPORT SHOW ...
timeTue, 02 Jan 2018 14:25:03 GMT
DFMEA REPORT SHOW ...
timeTue, 02 Jan 2018 14:29:09 GMT
BOM Form Longxiang Group Limited Mold information Longxiang Project No Basic information Mold basic information Project No. Mold base brand Mold base level ...
timeTue, 02 Jan 2018 14:30:40 GMT
Cutting Tooling Noticd Cutting Tooling Steel Notice P.O Tooling No. Resin Color Shrinkage Rate Tooling core Surface of ...
timeTue, 02 Jan 2018 15:56:35 GMT
Weekly Report Project Name: LXGL182 P.O.Date: 2-Apr-18 T1 Date: 30-Apr-18 Report Date: 2-Apr-17 This is a weekly ...
timeTue, 02 Jan 2018 15:57:38 GMT
CDContents: 1. Tooling 2D 2. Tooling 3D 3. Dimension Report 4. Photograph 5. Video
timeTue, 02 Jan 2018 16:01:40 GMT
3000 cycles testing for tooling ejecting system
timeTue, 02 Jan 2018 16:02:46 GMT
grass and ground pavers have a load bearing capacity up to 1000t/m²Supplied as 4 pavers (1sqm) pre-connected for rapid ease of installationManufactured from 100% recycled polymer grass pavers / ground reinforcement pavers are British manufacturedPavers filled with grass or gravel are SUDS source control compliantgrass pavers / gravel pavers allow a naturally pleasing, environmentally friendly & f...
timeMon, 08 Apr 2019 17:50:36 GMT
Car Parks / Coach Parks (Grass or Gravel)Overspill / overflow grass car parksEmergency Service (Fire Access routes)HGV service access routesAircraft taxiways & helipadsWalkways and disabled access routes (DDA)Golf buggy pathsDriveways and residential lawn parkingSUDS source control
timeMon, 08 Apr 2019 17:12:38 GMT
Grass grid uses a modified high molecular HDPE and PP as raw material, Material adopt high pressure injection forming technology to suppress the nest bee continuous shell, three-dimensional space and certain support height and strength, green environmental protection, completely Recyclable. It realizes a perfect combination of parking lots with lawn. Grass paver has good properties pressure-resis...
timeMon, 08 Apr 2019 17:10:38 GMT
The DraftAngleAnalysis command visually evaluates surface draft-angle using false-color analysis.Draft angle is used to design injection-molded parts that must eject from molds.Steps1. Select objects.2. In the Draft Angle dialog box, set the angle for the color display.The draft angle depends on the construction plane orientation. When the surface is vertical/perpendicular to the construction plan...
timeWed, 03 Apr 2019 16:55:24 GMT
With the definition of the parting plane and all necessary shut-offs,the core insert and cavity insert have been completely separated.To create the cavity and core inserts,the length,width,and height of the inserts must be defined.All of these requirements suggest making the core and cavity inserts as large as possible.For smaller molded parts,increasing the sizing the core and cavity inserts may ...
timeWed, 03 Apr 2019 16:53:07 GMT
The important consideration should be end product and what your definition of "REGRIND" is. Reprocessing your own internal scrap (if kept clean and uncontaminated with anything else) is a significantly different question basis than using unknown or unclassified "regrind" from outside sources.As to the end ...
timeMon, 12 Mar 2018 16:27:39 GMT
It's a small plastic injected piece that will be submitted to short period of time (2 seconds) of high temperature (95-105ºC approx.) in every cycle; this high temperature is produced by a filament where electric current passes through (like a house light bulb but hotter) for no mo...
timeMon, 12 Mar 2018 16:23:23 GMT
Gate types The two main gate systems are manually trimmed gates and automatically trimmed gates. The following examples show where they are used:1. Sprue gate: Used for large components, the gate mark is visible in component and no runner is required. e.g.: bucket molding (backside ...
timeTue, 27 Feb 2018 15:18:00 GMT
Ejection system types l Pin ejection—Cylindrical pins eject the finished component. In the case of square and rectangular components, a minimum of four pins (at the four corners) are required. In the case of cylindrical components, three equidistant pins (i.e. 120° apart) are requir...
timeTue, 27 Feb 2018 15:15:22 GMT
Hard Tooling -Steel/aluminum tools are used for the injection molding process for prototype or bridge, but these tools are mostly used for high volume production (100’s-100,000’s).-Steel/aluminum tools typically range in price from thousands to tens of thousands of dollars. And pend...
timeTue, 27 Feb 2018 15:01:30 GMT
Hard Tooling -Steel/aluminum tools are used for the injection molding process for prototype or bridge, but these tools are mostly used for high volume production (100’s-100,000’s).-Steel/aluminum tools typically range in price from thousands to tens of thousands of dollars. And pend...
timeTue, 27 Feb 2018 14:55:20 GMT
Longxiang as a experienced player in the line, we strive for customer satisfactions. So we ensure you that we will follow up every product we sell.Longxiang provide necessary technology and technical supports for all our products. We have decades of technicians available to assist in the as...
timeTue, 23 Jan 2018 19:13:03 GMT
Plastic MaterialFeaturesApplicable products POMLow friction coefficient,Good geometric stabilityEspecially suitable for the production of gear and bearing PA PA6Good elasticity,High impact strength,Water absorption is biggerSuitable for making general machinery parts, reduce friction wear parts, trans...
timeTue, 16 Jan 2018 16:31:28 GMT
In general, For plastic injection mold: 50% deposit, 30% before T1 sample, 20% after you confirm the sampleFor plastic injection parts: 50% deposit, 50% before shipmentFor rapid prototype: 100% deposit
timeTue, 02 Jan 2018 13:35:59 GMT
In general1-2 days for DFMEA report2-3 days for mold design and making mold drawing25-40 days for mold making.